Electrical Sub-station
Coordinate layout area of work with Ms. Utility and Heffron verifying elevations match design criteria.
F&I const. fencing around the LOD, signage, road barriers, silt fence/sediment control, in phases according to the Traffic Control Plan provided by client.
Saw cut and remove the asphalt/concrete in the phases as indicated by client.
Provided with fencing, shoring, signage, sediment control, machines, and road plates.
Remove excavated soil/stone from site daily and dispose at local recycle/dump facility.
Infill the concrete saddles with concrete to encase the newly installed conduit serving the new prefabbed structure.
Furnish and install concrete pedestal supports.
Furnish and install new pipe bollards painted safety yellow w/ red reflective tape and a top cap.